Case Study: How Early Project Review Prevented Cost Overruns and Schedule Delays

 Cost overruns are one of the most common challenges in capital-intensive projects. Across energy, industrial, and infrastructure sectors, many projects exceed their original budgets not because of poor execution alone, but due to weaknesses embedded in early-stage decisions. This case study illustrates how an early independent project review helped prevent cost overruns and schedule delays by identifying risks before construction began.


Cost overruns are one of the most common challenges in capital-intensive projects. Across energy, industrial, and infrastructure sectors, many projects exceed their original budgets not because of poor execution alone, but due to weaknesses embedded in early-stage decisions. This case study illustrates how an early independent project review helped prevent cost overruns and schedule delays by identifying risks before construction began.

The case presented here is a representative example based on real project review experience. Specific details have been generalized to preserve confidentiality while maintaining technical and commercial relevance.


Project Background

The project involved the development of a mid-scale industrial energy facility intended to supply power and utilities to an industrial estate. The project was promoted by a private investor group and was approaching Final Investment Decision (FID). At this stage, the project had:

  • A completed Feasibility Study
  • Preliminary Front-End Engineering Design (FEED)
  • An indicative EPC cost proposal

Despite apparent readiness, the investors requested an independent project review to validate assumptions, assess risks, and confirm investment readiness.


Initial Project Assumptions

The original project plan was based on several key assumptions:

  • EPC execution under a lump-sum turnkey contract
  • An aggressive construction schedule aligned with early revenue targets
  • Capital cost estimates derived from limited FEED documentation
  • Technology selection based on vendor recommendations

While these assumptions appeared reasonable on the surface, they had not been independently challenged.


Scope of the Early Project Review

The independent project review focused on four main areas:

  1. Technical maturity and FEED completeness
  2. Cost and schedule assumptions
  3. EPC contract structure and risk allocation
  4. Key execution and operational risks

The objective was not to redesign the project, but to assess whether the project was truly ready to proceed to EPC award and construction.


Key Issues Identified During the Review

1. Incomplete FEED Definition

The review revealed that several critical FEED deliverables were either incomplete or missing, including:

  • Preliminary P&IDs for auxiliary systems
  • Utility balance calculations
  • Plot plan optimization

These gaps increased the likelihood of scope growth during detailed engineering and construction.


2. Underestimated Capital Costs

The EPC cost estimate was found to be optimistic. Key cost drivers that were underestimated included:

  • Electrical and instrumentation scope
  • Civil works related to site conditions
  • Commissioning and start-up activities

Benchmarking against similar projects indicated a potential cost overrun risk of 15–25%.


3. Schedule Risks

The proposed schedule did not adequately account for:

  • Long-lead equipment procurement
  • Permitting and regulatory approval timelines
  • Interface coordination between contractors

The review concluded that the schedule was aggressive and carried a high risk of delay.


4. EPC Contract Risk Allocation

The draft EPC contract contained several clauses that shifted excessive risk back to the project owner, including:

  • Broad exclusions hidden in appendices
  • Limited remedies for underperformance
  • Ambiguous change management provisions

These issues would likely have led to disputes during execution.


Recommended Corrective Actions

Based on the findings, the independent reviewers recommended:

  • Extending the FEED phase to close identified technical gaps
  • Revising capital cost estimates using a transparent, bottom-up approach
  • Adjusting the project schedule to reflect realistic execution logic
  • Rebalancing EPC contract risk allocation and clarifying scope

Although these recommendations required additional upfront effort, they significantly reduced downstream risk.


Impact on Project Outcome

Following implementation of the recommendations:

  • The project budget was revised upward before FID, avoiding surprise overruns later
  • EPC tendering was based on a clearer and more complete scope
  • Contractor bids were more consistent and comparable
  • The final EPC contract contained fewer exclusions and clearer performance guarantees

As a result, the project proceeded to construction with improved predictability and significantly reduced claim exposure.


Lessons Learned for Investors and Project Owners

This case highlights several critical lessons:

  • Early-stage optimism must be balanced with objective review
  • FEED completeness is directly linked to cost and schedule certainty
  • EPC contracts do not eliminate risk unless properly structured
  • Early independent reviews are far more cost-effective than fixing problems during construction

The cost of the early project review represented a fraction of the potential cost overruns it helped prevent.


Why Early Project Reviews Add Value

Independent project reviews provide:

  • Objective assessment of technical and commercial assumptions
  • Early identification of hidden risks
  • Decision support before irreversible commitments are made

For investors, this approach protects capital and improves long-term project performance.


Conclusion

This case study demonstrates that cost overruns are not inevitable. Many can be prevented by identifying and addressing risks early in the project lifecycle. Early independent project reviews enable informed decision-making, reduce uncertainty, and significantly improve the likelihood of project success.

For capital-intensive projects, the question is not whether a project review is affordable—but whether proceeding without one is acceptable.


How Our Consulting Services Support Early Project Reviews

At Engineering Projects & Industry Review Hub, we support investors and project owners through:

  • Independent project and investment readiness reviews
  • FEED and EPC validation
  • Cost, schedule, and risk assessment
  • Technical and commercial due diligence

Our role is to help clients make confident, well-informed decisions before capital is committed.


How We Support Investors and Project Owners

We provide independent feasibility preparation & reviews, FEED advisory, and EPC risk assessments to support informed investment decisions.

📩 Contact us: afakar@gmail.com

WhatsApp: +62 813-6864-3249

EPC Contracts Explained: What Project Owners and Investors Must Review

Engineering, Procurement, and Construction (EPC) contracts are widely used in industrial, energy, and infrastructure projects because they promise simplicity: a single contractor responsible for delivering a complete facility at an agreed price and schedule. For project owners and investors, EPC contracts are often perceived as a way to transfer risk and achieve cost certainty.

Engineering, Procurement, and Construction (EPC) contracts are widely used in industrial, energy, and infrastructure projects because they promise simplicity: a single contractor responsible for delivering a complete facility at an agreed price and schedule. For project owners and investors, EPC contracts are often perceived as a way to transfer risk and achieve cost certainty.

However, many projects experience cost overruns, delays, and disputes despite being executed under EPC arrangements. The reason is simple: an EPC contract only works as intended when it is properly structured, clearly defined, and thoroughly reviewed before approval.

This article explains the key elements that project owners and investors must review before signing an EPC contract—and why independent EPC reviews are critical to protecting capital.


What Is an EPC Contract?

An EPC contract is a project delivery model where a single contractor is responsible for:

  • Engineering and design
  • Procurement of equipment and materials
  • Construction, installation, and commissioning

In theory, the EPC contractor delivers a “turnkey” facility that meets agreed performance requirements at a fixed price and schedule. In practice, the effectiveness of an EPC contract depends heavily on how risks, scope, and responsibilities are defined.


Why EPC Contracts Often Fail to Deliver Expected Outcomes

EPC contracts fail not because the model is flawed, but because they are often:

  • Based on incomplete FEED or poorly defined scope
  • Negotiated under time pressure
  • Structured with unbalanced risk allocation

When uncertainties are pushed into the contract rather than resolved upfront, disputes become inevitable during execution.


Key EPC Contract Elements Investors Must Review

1. Scope of Work Definition

The most critical part of any EPC contract is the scope of work. Investors should verify:

  • That the scope aligns with FEED deliverables
  • Clear definition of battery limits and interfaces
  • Explicit inclusions, exclusions, and assumptions

Ambiguous scope leads directly to change orders and claims.


2. Contract Price Structure

While EPC contracts are often labeled as “lump sum,” investors should understand:

  • What assumptions underpin the pricing
  • Whether escalation, taxes, and duties are included
  • How contingencies are handled

An unrealistically low EPC price is often a warning sign rather than a benefit.


3. Risk Allocation

One of the most misunderstood aspects of EPC contracts is risk transfer. Investors should carefully review:

  • Who bears design risk
  • Who is responsible for regulatory changes
  • Force majeure and change-in-law provisions

Risk should be allocated to the party best able to manage it. Unbalanced risk allocation often results in disputes rather than risk elimination.


4. Schedule and Liquidated Damages

Schedule commitments are critical to project economics. EPC contracts typically include:

  • Key milestones
  • Guaranteed completion dates
  • Delay liquidated damages (LDs)

Investors should assess whether the proposed schedule is realistic and whether LDs are sufficient to compensate for delays without incentivizing claims-driven behavior.


5. Performance Guarantees

Performance guarantees define whether the completed facility meets agreed output, efficiency, or quality targets. Investors should review:

  • Clear and measurable performance criteria
  • Testing procedures and acceptance standards
  • Remedies if performance is not achieved

Weak or poorly defined guarantees expose investors to long-term operational underperformance.


6. Change Management and Variations

Even well-prepared projects experience changes. EPC contracts must clearly define:

  • How variations are initiated and approved
  • Pricing mechanisms for changes
  • Impact on schedule and guarantees

Poorly defined change management processes are a major source of cost escalation.


The Link Between FEED Quality and EPC Success

Strong FEED significantly improves EPC outcomes by:

  • Reducing uncertainty in scope and pricing
  • Allowing fair comparison of EPC bids
  • Minimizing post-award changes

Projects that move into EPC without adequate FEED often pay for that decision through claims, delays, and strained relationships.


Common EPC Contract Red Flags

Investors and project owners should be cautious if they encounter:

  • EPC contracts based on incomplete or conceptual FEED
  • Excessive exclusions hidden in appendices
  • Performance guarantees without meaningful remedies
  • Aggressive schedules unsupported by execution logic
  • Limited transparency in cost assumptions

These red flags often signal future disputes and budget overruns.


Why Independent EPC Contract Reviews Matter

EPC contracts are typically drafted by contractors or project sponsors with commercial objectives. Independent EPC reviews provide:

  • Objective assessment of technical and commercial risks
  • Verification of alignment with FEED assumptions
  • Benchmarking against industry best practices

For investors, lenders, and joint venture partners, independent EPC reviews are a critical part of technical due diligence.


Conclusion

EPC contracts can be effective tools for delivering complex projects—but only when they are properly structured and reviewed. For project owners and investors, the key is not to assume that an EPC contract automatically transfers risk, but to understand where risks truly reside.

Thorough EPC contract reviews, supported by strong FEED and independent expertise, are essential to protecting capital and achieving predictable project outcomes.


How Our Consulting Services Support EPC Reviews

At Engineering Projects & Industry Review Hub, we support investors and project owners through:

  • Independent EPC contract reviews
  • Technical and commercial due diligence
  • Risk allocation and scope validation
  • EPC readiness and bid evaluation support

Our focus is to help decision-makers enter EPC contracts with clarity, balance, and confidence.


How We Support Investors and Project Owners

We provide independent feasibility preparation & reviews, FEED advisory, and EPC risk assessments to support informed investment decisions.