Translate

Case Study: How Early Project Review Prevented Cost Overruns and Schedule Delays

 Cost overruns are one of the most common challenges in capital-intensive projects. Across energy, industrial, and infrastructure sectors, many projects exceed their original budgets not because of poor execution alone, but due to weaknesses embedded in early-stage decisions. This case study illustrates how an early independent project review helped prevent cost overruns and schedule delays by identifying risks before construction began.


Cost overruns are one of the most common challenges in capital-intensive projects. Across energy, industrial, and infrastructure sectors, many projects exceed their original budgets not because of poor execution alone, but due to weaknesses embedded in early-stage decisions. This case study illustrates how an early independent project review helped prevent cost overruns and schedule delays by identifying risks before construction began.

The case presented here is a representative example based on real project review experience. Specific details have been generalized to preserve confidentiality while maintaining technical and commercial relevance.


Project Background

The project involved the development of a mid-scale industrial energy facility intended to supply power and utilities to an industrial estate. The project was promoted by a private investor group and was approaching Final Investment Decision (FID). At this stage, the project had:

  • A completed Feasibility Study
  • Preliminary Front-End Engineering Design (FEED)
  • An indicative EPC cost proposal

Despite apparent readiness, the investors requested an independent project review to validate assumptions, assess risks, and confirm investment readiness.


Initial Project Assumptions

The original project plan was based on several key assumptions:

  • EPC execution under a lump-sum turnkey contract
  • An aggressive construction schedule aligned with early revenue targets
  • Capital cost estimates derived from limited FEED documentation
  • Technology selection based on vendor recommendations

While these assumptions appeared reasonable on the surface, they had not been independently challenged.


Scope of the Early Project Review

The independent project review focused on four main areas:

  1. Technical maturity and FEED completeness
  2. Cost and schedule assumptions
  3. EPC contract structure and risk allocation
  4. Key execution and operational risks

The objective was not to redesign the project, but to assess whether the project was truly ready to proceed to EPC award and construction.


Key Issues Identified During the Review

1. Incomplete FEED Definition

The review revealed that several critical FEED deliverables were either incomplete or missing, including:

  • Preliminary P&IDs for auxiliary systems
  • Utility balance calculations
  • Plot plan optimization

These gaps increased the likelihood of scope growth during detailed engineering and construction.


2. Underestimated Capital Costs

The EPC cost estimate was found to be optimistic. Key cost drivers that were underestimated included:

  • Electrical and instrumentation scope
  • Civil works related to site conditions
  • Commissioning and start-up activities

Benchmarking against similar projects indicated a potential cost overrun risk of 15–25%.


3. Schedule Risks

The proposed schedule did not adequately account for:

  • Long-lead equipment procurement
  • Permitting and regulatory approval timelines
  • Interface coordination between contractors

The review concluded that the schedule was aggressive and carried a high risk of delay.


4. EPC Contract Risk Allocation

The draft EPC contract contained several clauses that shifted excessive risk back to the project owner, including:

  • Broad exclusions hidden in appendices
  • Limited remedies for underperformance
  • Ambiguous change management provisions

These issues would likely have led to disputes during execution.


Recommended Corrective Actions

Based on the findings, the independent reviewers recommended:

  • Extending the FEED phase to close identified technical gaps
  • Revising capital cost estimates using a transparent, bottom-up approach
  • Adjusting the project schedule to reflect realistic execution logic
  • Rebalancing EPC contract risk allocation and clarifying scope

Although these recommendations required additional upfront effort, they significantly reduced downstream risk.


Impact on Project Outcome

Following implementation of the recommendations:

  • The project budget was revised upward before FID, avoiding surprise overruns later
  • EPC tendering was based on a clearer and more complete scope
  • Contractor bids were more consistent and comparable
  • The final EPC contract contained fewer exclusions and clearer performance guarantees

As a result, the project proceeded to construction with improved predictability and significantly reduced claim exposure.


Lessons Learned for Investors and Project Owners

This case highlights several critical lessons:

  • Early-stage optimism must be balanced with objective review
  • FEED completeness is directly linked to cost and schedule certainty
  • EPC contracts do not eliminate risk unless properly structured
  • Early independent reviews are far more cost-effective than fixing problems during construction

The cost of the early project review represented a fraction of the potential cost overruns it helped prevent.


Why Early Project Reviews Add Value

Independent project reviews provide:

  • Objective assessment of technical and commercial assumptions
  • Early identification of hidden risks
  • Decision support before irreversible commitments are made

For investors, this approach protects capital and improves long-term project performance.


Conclusion

This case study demonstrates that cost overruns are not inevitable. Many can be prevented by identifying and addressing risks early in the project lifecycle. Early independent project reviews enable informed decision-making, reduce uncertainty, and significantly improve the likelihood of project success.

For capital-intensive projects, the question is not whether a project review is affordable—but whether proceeding without one is acceptable.


How Our Consulting Services Support Early Project Reviews

At Engineering Projects & Industry Review Hub, we support investors and project owners through:

  • Independent project and investment readiness reviews
  • FEED and EPC validation
  • Cost, schedule, and risk assessment
  • Technical and commercial due diligence

Our role is to help clients make confident, well-informed decisions before capital is committed.


How We Support Investors and Project Owners

We provide independent feasibility preparation & reviews, FEED advisory, and EPC risk assessments to support informed investment decisions.

📩 Contact us: afakar@gmail.com

WhatsApp: +62 813-6864-3249

No comments:

Other Articles

oclkaf03bnr1

at26914806

at26997598

Followers